All Plasterboard sheets are now up in the living area of the house, just a few to be added on the void storage space ceiling, 
Plastering is nearly complete, just the stairwell space to be completed.

Kitchen units are in, ready for the worktop to be templated.
Master En-Suite is finished, tiled, plumbed and all bathroom units installed.

Balcony steel frame needs to be cut and welded. The glass balcony surround is purchased and waiting on these steel support rails being assembled. 
First fix wiring and plumbing is complete, Heat Pumps are plumbed and ready to be commissioned to provide our hot water & heating.
Car Port footings are laid, pillars & pad to be concreted prior to Oak Roof Support Frame to be erected & roof waterproofing & slates to be installed.
Oak frame sanding still to be completed, as there is a lot of it !

Main entrance door is fully fitted and we are now all secure. 
Cellar Staircase trapdoor created, welded and installed. Plastering of walls completed and kitchen/dining/lounge flooring is laid..

Tiling of other bathrooms has started, First Floor En-Suite is tiled and flooring is laid, just needs walls finishing then shower & bath can be fully sited and installed